Completeness: what it checks and how to read it

Completeness shows what data has arrived, by facility, emission source and month.

Written by Misha Cajic

Completeness shows what data has arrived, by facility, emission source and month.

It answers one question: for each site and each source, is there data for every day of the period?

This is the Completeness screen under Data Management. The Completeness page inside an assessment, under Accounts, is a different check: it ties your general ledger to your trial balances. See Check your general ledger is complete against your trial balances.

What it compares

Completeness compares the days covered by your activity data against the days the facility was open in that month.

A record that covers a billing period counts for every day in that period. A quarterly electricity bill therefore fills three months.

The figure is coverage of time. It is not a percentage of spend and not a percentage of emissions.

How do I read the Completeness grid?

On the Completeness screen, each parent row is a facility. Each child row under it is an emission source at that facility. One column represents one month.

Metered sources show days, as "24 / 31". Sources recorded as one-off transactions show a record count, as "3 records".

The right-hand column shows tCO2e for that row.

What each cell state means on the Completeness screen

This table shows each cell state on the Completeness screen and what it means.

State

Meaning

Complete

Every day of the month is covered

Partial

Some days are covered, but not all

Missing

No data, and the month has ended

Awaiting

No data, and the month has not ended yet

Arrived

At least one record, for sources counted by record

Check

No records in a month that has ended, for sources counted by record

An Awaiting cell is not a gap. The month is still running.

A Check cell is a candidate gap rather than a confirmed one. Some sources genuinely have no activity in a given month.

Find the gaps

  1. In the sidebar, under Data Management, select Completeness.

  2. Set the From and To months.

  3. Turn on Gaps only.

The grid then shows only rows with a Missing, Partial or Check state.

Act on a gap

Select any cell to open the Emissions Hub, filtered to that facility, emission source and month. You correct the data there.

Completeness itself is read-only.

What does the Completeness screen leave out?

The Completeness screen covers every scope and every source of activity data. Three things do not appear on it:

  • Rows not attributed to a facility. Set the facility on those rows and they appear.

  • Rows whose input unit type is unknown.

  • Facilities excluded from your boundary.

Why does the Completeness screen say it isn't switched on?

The Completeness screen is enabled per organisation. If you see "Completeness isn't switched on yet", contact Avarni.

Did this answer your question?